Users with the "Edit Contracts" permission can easily backdate contracts that are in either Pending or Finished status.
How to Backdate & Start a Pending Contract:
- Locate the pending contract and click the Contract ID
- On the contract page, select the "Manage" tab
- Scroll to the bottom of the page and click "Start Contract"
- Depending on the contract's Program Settings, you may need to click "continue without credit card" for this button to be clickable (screenshot)
- In this menu, if needed, edit the date(s) & time(s) for the Actual Start and Scheduled Finish
- Note: the Scheduled Finish Date/Time must be after the Actual Start Date/Time
- Enter the reason the contract had to be backdated
- Click "Start Contract"
- The contract should now be started with the backdated actual start date & time
- The contract should now be started with the backdated actual start date & time
How to Edit the Actual Start or Finish Date/Time of a Finished Contract:
- Locate the finished contract
- Locate the customer's profile and click their name
- Select the "Contracts" tab near the top of the page
- Click on the Contract ID
- On the contract page, select the "Manage" tab
- In the "Booking Summary" section, click the "Edit" button in the top right of the box.
- Edit the date(s) and/or times(s)
- Enter the reason for the edit(s)
- Click "Save" in the bottom right